State Estimation and Determination of Flexibility Potential in Medium Voltage Networks*
TU Dortmund University, 44227 Dortmund, Germany
* This work was supported by the German Federal Ministry for Economic Affairs and Energy (BMWi) in the course of the project IDEAL (FKZ: 03ET7557A).
† Corresponding author: florian.rewald@tu-dortmund.de
Published online: 15 October 2019
This paper describes how flexibility of medium voltage systems can be used for operation of high voltage systems. This is explained using the example of a congestion management system for high voltage networks developed in the research project IDEAL. First, it is explained to what extent flexibility is required for high voltage system operation. After that, the entire congestion management system with flexibility of medium voltage systems is presented. Then, methodology for observability analysis, state estimation and determination of flexibility potential is shown. Finally, the implementation of the methodology in two real medium voltage systems is described.
© The Authors, published by EDP Sciences, 2019
This is an Open Access article distributed under the terms of the Creative Commons Attribution License 4.0, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.
Current usage metrics show cumulative count of Article Views (full-text article views including HTML views, PDF and ePub downloads, according to the available data) and Abstracts Views on Vision4Press platform.
Data correspond to usage on the plateform after 2015. The current usage metrics is available 48-96 hours after online publication and is updated daily on week days.
Initial download of the metrics may take a while.