AMP 2010 – International Workshop on Ageing Management of Nuclear Power Plants and Waste Disposal Structures (EFC Event 334)
|
|
---|---|---|
Article Number | 01005 | |
Number of page(s) | 12 | |
Section | Aging Management Program | |
DOI | https://doi.org/10.1051/epjconf/20111201005 | |
Published online | 12 April 2011 |
https://doi.org/10.1051/epjconf/20111201005
Aging management program of the reactor building concrete at Point Lepreau Generating Station
1 AMEC Earth & Environmental, Hamilton, Ontario, Canada
2 New Brunswick Power Nuclear, Point Lepreau, New Brunswick, Canada
3 Atomic Energy of Canada Limited, Chalk River, Ontario, Canada
a e-mail: corina.aldea@amec.com
In order for New Brunswick Power Nuclear (NBPN) to control the risks of degradation of the concrete reactor building at the Point Lepreau Generating Station (PLGS) the development of an aging management plan (AMP) was initiated. The intention of this plan was to determine the requirements for specific structural components of concrete of the reactor building that require regular inspection and maintenance to ensure the safe and reliable operation of the plant. The document is currently in draft form and presents an integrated methodology for the application of an AMP for the concrete of the reactor building. The current AMP addresses the reactor building structure and various components, such as joint sealant and liners that are integral to the structure. It does not include internal components housed within the structure. This paper provides background information regarding the document developed and the strategy developed to manage potential degradation of the concrete of the reactor building, as well as specific programs and preventive and corrective maintenance activities initiated.
© Owned by the authors, published by EDP Sciences, 2011
Current usage metrics show cumulative count of Article Views (full-text article views including HTML views, PDF and ePub downloads, according to the available data) and Abstracts Views on Vision4Press platform.
Data correspond to usage on the plateform after 2015. The current usage metrics is available 48-96 hours after online publication and is updated daily on week days.
Initial download of the metrics may take a while.