Dose rate evaluation of workers on the operation floor in Fukushima-Daiichi Unit 3
1 Toshiba Corporation, Yokohama, 235-8523, Japan
2 Tokyo Nuclear Services Corporation, Tokyo, 110-0016, Japan
3 Tokyo Electric Power Company Holdings, Inc., Tokyo, 100-8560, Japan
* Corresponding author: kaoru2.matsushita@toshiba.co.jp
Published online: 25 September 2017
At Fukushima Daiichi Nuclear Power Plant Unit 3, installation of a fuel handling machine is planned to support the removal of spent fuel. The dose rates at the workplace were calculated based on the source distribution measured using a collimator in order to confirm that the dose rates on the operation floor were within a manageable range. It was confirmed that the accuracy of the source distribution was C/M = 1.0-2.4. These dose rates were then used to plan the work on the operation floor.
© The Authors, published by EDP Sciences, 2017
This is an Open Access article distributed under the terms of the Creative Commons Attribution License 4.0, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.
Current usage metrics show cumulative count of Article Views (full-text article views including HTML views, PDF and ePub downloads, according to the available data) and Abstracts Views on Vision4Press platform.
Data correspond to usage on the plateform after 2015. The current usage metrics is available 48-96 hours after online publication and is updated daily on week days.
Initial download of the metrics may take a while.